Unfortunatly i have closed the sprint before the deadline. is there way to open again?
Hello Ramesh,
Welcome to community :)
Please try
To reopen a sprint:
If not already there, navigate to your project.
From your project’s sidebar, select Reports.
If you’re using a company-managed project, select the Sprint Report. If you’re using a team-managed project, select either the Burnup report or the Sprint burndown chart.
Select the relevant sprint from the sprint drop-down.
Select more (…) > Reopen sprint.
Select Reopen.
Thank you ,
Prachi
You can find the documentation here, but this can only be done if the project used is a Company managed project.
https://support.atlassian.com/jira-software-cloud/docs/reopen-a-sprint/
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.