In JIRA Work Management, i can create a Sub Task under Task as follows. But can't I create another sub task under the Sub Task? If I can, what should I do?
You cannot create a Sub-task under a Sub-task, however, if you add "Epics" to your Issue Types for the project, you can create a Sub-task under a Task under an Epic.
You can add as many Sub-tasks as you need, but they will all fall under a Task.
Epic -> Task -> Sub-task
Sub-task
Sub-task
You cannot do Epic -> Task -> Sub-task -> Sub-task
(If you hover over the Task, the + symbol will appear)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sorry for any confusion. All the Sub-tasks will be on the same level. A sub-task cannot have a work item below it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @ks.hyeon
just to add to Joel's great answer: The only way to model something hierarchy levels below sub-tasks in Jira is through issue links. You can create any issue link between any two issues, so you can always do e.g. a is parent of / is child of issue link between one sub-task and another.
The problem is that Jira doesn't naturally understand such issue link as a hierarchy level, so you won't see them nested in e.g. Jira Work Management's list view. There are, however, Marketplace apps that can help with this. E.g., my team and I work on an app named JXL for Jira in which you can configure custom issue hierarchies, based on Jira's built-in parent/child relationships, and/or based on issue links. This is how it looks in action:
Any questions just let me know,
Best,
Hannes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How to parent two sub-tasks ? I can only parent from sub to Task or Story and from Task to Epic.
so @Joel Garner is completely right .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Hannes Obweger - JXL for Jira
How did you set the structure above?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thank you for also reaching out to our support team - we'll be working with you on this via the support ticket.
Best,
Hannes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello from Peru
I've recently discovered Jira's powerful Project managment features
But, I've got same question about sub-levels, on real world any develpment feature includes more and more deeper details.
So , any chance to get more subleves on future ?
Greetings from Lima
FER
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.