Create several sprints in just one project

Laura Vallejo
Contributor
September 4, 2020

I am trying to use Jira to manage a generic project (it is not going to be a development project). I was thinking one sprint could be a project milestone. But in a project, sometimes several milestone could be active. 

So, is there any way to have 2 or more sprint active?

Thank you!

1 answer

0 votes
Callum Carlile _Automation Consultants_
Community Champion
September 4, 2020

@Laura Vallejo This outlines how you can enable parallel sprints in Jira. You will need to be a Jira administrator to make this change.

Bear in mind that this is a Jira-wide setting which will enable parallel sprints for all projects, so if you're not a site admin then it might have to be consulted with them first!

Laura Vallejo
Contributor
September 4, 2020

I have searched in the administration panel without success. Where can I changed the settings?

Thank you very much for your help

Sramanth Pandeti
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 4, 2020

@Laura Vallejo Navigate to Jira Administration Settings (Top right) -> Applications -> Jira software configuration to enable/disable the parallel sprints feature. 