Kyaw Wanna April 17, 2019

Hi,

When I search in the story (issue), it does not include "create sub-task" menu.

I would appreciate if you may suggest on this.

URL: https://kyawwanna.atlassian.net

Project Name: Wordpress Website Design Agency

Story Name:

“As a potential customer, I want to see that the designer’s website looks professional and is using WordPress, so I can feel confident I am in the right place.”

 

Regards,

Kyaw

2 answers

1 accepted

0 votes
Answer accepted
Tarun Sapra
Community Champion
April 18, 2019

Hello @Kyaw Wanna 

Classic projects on Jira cloud do have the ability to create sub-tasks as I just checked and it's working fine for me, please see the screenshot attached.

image.png

Kyaw Wanna April 18, 2019

Hi,

I got this. Thanks so much.

Regards,

Kyaw

Like Tarun Sapra likes this
Tarun Sapra
Community Champion
April 18, 2019

Hello @Kyaw Wanna 

Glad to know that it's working for you now, please accept/upvote the answer so that other users are helped as well. thanks.

1 vote
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 17, 2019

Hello,

It could mean that the issue type scheme for the project does not include subtasks. You should add a sub task to the issue type scheme.

You can find more info here:

https://confluence.atlassian.com/adminjiracloud/adding-editing-and-deleting-an-issue-type-scheme-844500754.html

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 17, 2019

Or if you use a next-gen project, then subtasks are not available for next-gen projects

Like Tarun Sapra likes this
Kyaw Wanna April 17, 2019

Hi,

When I checked the Issue Type Scheme, it's already included "Sub-task". And I thought I used the classic project not the next-gen.

Screen Shot 2562-04-18 at 11.46.58.png

Regards,

Kyaw

Suggest an answer