Hello
I have a question related to the Valocity report. Current I have below status on sprint board
I would like to calculate velocity based on below:
DO you think there is a way to achieve this in JIRA?
Velocity is a measure of how a team is performing in terms of how much it gets done against what the team committed to delivering in a specific time-box.
This is quite a simple measure - it's basically "done" vs "not done" at the end of the time-box.
Jira considers only the last column on a board as "done"
You can do what you want in the boards - put both "ready to deploy" and "completed" in the last column on the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks to this response I was finally able to make my reports work.
Since I did not have the DONE as the last column on my board, my Velocity Reports stopped working and the Sprints did not identify the DONE tasks as "completed" and tried moving them to the next Sprint or to the backlog.
In other words, thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Just wondering if Jira did any improvement on this behavior?
As a user am I able to configure that QA done, RC is considered completed user stories instead of just the Done column?
Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.