Days remaining in sprint gadget only displays work days?

Michael Arndt
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 3, 2019

So I have a sprint that's due on 5/14/19 which is 11 days away. The gadget says 6 days which I'm guessing is some odd workday calendar which doesn't include the actual due date or the current date.

Is there anyway to get it to just display calendar days?

 

 

1 answer

1 accepted

1 vote
Answer accepted
Ollie Guan
Community Champion
May 4, 2019

Hi @Michael Arndt ,

Working days settings allow you to highlight or exclude non-working days from reports and gadgets.

wd.png

BTW:

Currently, next-gen project does not have "Board settings", so it's not possible to configure the Working days.

https://jira.atlassian.com/browse/JSWCLOUD-17331?_ga=2.57563242.1396607561.1557018896-2036880908.1548031592

Please, click on vote and watch to receive updates about the feature.

Daniela Argento
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 16, 2020

I set the working days, region and time zone correctly, and Jira still does not show the correct days remaining. 