I want to display progress of either epic or taks in a rearch result.
I see the colum namded Progress. But even I chose it and added the colum, nothing is there.
The Progress column that you can add to search results reflects the time tracking information.
The light blue bar on top represents the Original Estimate.
The green bar below represents the time that has been logged.
The dark blue bar next to the green bar represents the time remaining.
If no Original Estimate time value has been entered and no time has been logged, then nothing will display.
If time has been logged but no Original Estimate was entered, then the light blue bar will be replaced by a grey bar. If a Remaining Time value was entered along with the time logged, that will be reflected in the green and dark blue bars.
If an Original Estimate has been entered and no time has been logged, it will look like this.
Thank you for answering my question.
I totally misunderstood the meaning of progress..
This progress is different from the status of subtasks.
Thanks again.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for answering my question.
I totally misunderstood the meaning of progress..
I thought this progress would be the status of subtasks.
Now I know why.
Thanks again.