Hello,

 

Imagine one developer has 3 task's:

A

B

C

Highest priority A, but B must be done on due date X, no matter A is completed or not.

How can developer see that in his dashboard, that day X he/she should pause A and start B if something bad happens?

1 answer

1 vote
Thomas Schlegel
Community Champion
May 14, 2018

Hi @Simas Jokubauskas

you can see your overdue issues with the following jql:

due <= now() and resolution is EMPTY 

Put a filter-result gadget on your dashboard, so you can always see your overdue issues.

SJ
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 14, 2018

Thank you for your prompt reply. But how can I see it in board? Without filtering and etc.

Thomas Schlegel
Community Champion
May 14, 2018

Here are the steps:

  • search: due <= now() and resolution is EMPTY 
  • save the filter
  • go to your dashboard
  • create a new dashboard
  • add a gadget "Filter result" to your dashboard
  • add your saved filter to the gadget and save it
ivanseligmann
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 4, 2024

Hi Thomas

 

What about using the due date to group data in a two-dimensional gadget, if I want to see a table with the status of the issues I have for the different due dates?

 