I have a custom state "Ready for Implementation" that sits between Backlog and "In Progress". This state was assigned to "To Do" - same as Backlog.
However, when I transition a story from Backlog to Ready for Implementation", the parent Epic shows this story as "In Progress", whereas it should show it as "To Do".
Any ideas? Am I missing something?
The progress shown in the epic is based on the statusCategory, not on the actual status. So, is the category for the "Ready for Implementation" set to In progress? If you look at the color of the status (gray = to do, blue = in progress, green = done) what color is it?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.