We have our project broken into epics >> stories >> tasks and I had a question about story point estimation for each
Should Sum( all tasks under a story ) = Total points for a story? ( or do you stop points at story level )?
AND
Sum( all stories under an epic ) = Total points for an epic?
If so, what is the best way to go about making sure these are in sync without constantly checking the math. Here's the problem I am facing. We have an epic that we do not know much about..except that is it a Xlarge effort. If I assign it 21 points then start breaking into stories and tasks, I am concerned that the story points for the stories in this epic may exceed 21.
Hi Ravina,
This is a limitation on JIRA for now; JSWSERVER-8726. Stories' estimation does not sum up to the Epic's estimation. At the moment, JIRA will treat Epic's estimation separately to it's linked Stories.
You may look at some third-party plugins, according to this Community Thread, Epic Sum Up plugin might do the trick.
I hope that this helps.
Cheers,
Moga
Why on earth is such a simple feature, which a Google search will clearly indicate is a basic expectation of most users, left as an implementation exercise for a Marketplace developer who charges the cost of Jira (ie the whole platform) for what amounts to a trivial enhancement - (or even a bugfix).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.