Hi all,

is it possible to have other standard fields for taks and sub-tasks in one projekt? If its possible how can i adjust them?

 

thanks

1 answer

1 accepted

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 6, 2019

Hello,

Go to project settings -> screens and add more field to the screens.

Deleted user March 7, 2019

But this adds only more fields to the issues. I want to know if its possible to have a completely other fields for tasks and subtasks in one project

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 7, 2019

It is possible. Create different screens for Tasks and Subtasks. Create 2 different screen schemes. Then add these two screen schemes to the issue type screen scheme, which you use for the project, and associate each of the screen schemes, you created, to the correct issue type.

You can find more info here:

https://confluence.atlassian.com/adminjiraserver/associating-a-screen-with-an-issue-operation-938847289.html

https://confluence.atlassian.com/adminjiraserver0713/associating-screen-and-issue-operation-mappings-with-an-issue-type-964983582.html

Deleted user March 7, 2019

Thanks now it works

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 7, 2019

You are most welcome!

Suggest an answer

Log in or Sign up to answer
TAGS
AUG Leaders

Atlassian Community Events