Find sum of remaining estimes for a sprint?

Claus Østergaard Pedersen
Contributor
August 24, 2021

Hi,

I'm having trouble finding a way to see the total sum of Remaining Estimates (hours) for sprints.

Does anybody have an idea of how I can find this information?

As far as I can tell, there isn't a way to show it in the Backlog, as remaining estimate cant be chosen as Estimation Statistic (I know that I can add Remaining Estimate to the issue cards, but that doesn't give me the sum for the entire sprint) . Likewise, I cant find any gadgets in the Dashboards that will summarize the Remaining Estimates for a sprint.

I hope someone can point me in the right direction, and I'll much appreciate any suggestions. 

Best regards,

Claus

1 answer

1 accepted

1 vote
Answer accepted
Guilhem Dupuy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 24, 2021

Hello @Claus Østergaard Pedersen ,

Indeed that's a though one, you can try using the "Burndown Chart" gadget from a dashboard;

Then, you would have to go to your board settings, in the "Estimation" parameters and select the "Remaining estimate and ... " option :

estimation.png

Then your burndown chart should decrease depending on the remaining estimate, hence you'll be able to know the total remaining estimate of the sprint i guess.

 

Let me know how it goes,

Guilhem

Claus Østergaard Pedersen
Contributor
August 24, 2021

Hi Guilhem,

First off all, thanks a lot for your quick reply!

I tried what you suggested, and I can now see the total Remaining Estimate for the sprint in the Sprint Burndown Gadget on my dashboard.

I do wish there was alternative ways to get this information, so that you wouldn't have to "eyeball" it from a chart, as this exercise gets increasingly difficult if the scope of the sprint is changed when the sprint is active.

It would be nice if you could ad a sum total in, lets say, the filter results gadget in Dashboards.

 

Best regards

Claus

Guilhem Dupuy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 24, 2021

Hi @Claus Østergaard Pedersen ,

You're welcome :) 
I know it's not perfect, but unfortunately, as far as I know there is no way to obtain the information you need in Jira.

Maybe you could try with the "Workload Pie Chart" gadget if it's available in your instance (it may come with the Tempo app so I'm not 100% sure you'll be able to use it).

Let me know how it goes !

Like # people like this
Claus Østergaard Pedersen
Contributor
August 25, 2021

Hi @Guilhem Dupuy 

The "Workload Pie Chart" is actually pretty good! As far as I can tell, it shows the total of "Remaining Estimate" when you choose "Current Estimate" in "Time field to report on".

Thanks a lot for you suggestions!

Best regards

Claus

Like Guilhem Dupuy likes this
Guilhem Dupuy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2021

Happy to help !

You're welcome Claus

Rashmi Ratnani
Contributor
May 30, 2024

Hello @Guilhem Dupuy 

It's an old thread but hopefully you can still help me :)

Where can I find the "Workload Pie Chart"? 

I am still looking for a way to report as @Claus Østergaard Pedersen mentioned in the original post. Sprint Committed Hours vs. Sprint Remaining Hours (sum of all incl. sub-tasks). 

I have made a simple query which gives me a sum per PBI. But is there a way to get a total directly in Jira, instead of having to download this to excel and then summing up. 
sprint report - community question.jpg

 

Thanks. 

/RR

Claus Østergaard Pedersen
Contributor
May 31, 2024

Hi @Rashmi Ratnani 

The "Workload Pie Chart" is a dashboard gadget.

So you would have to save your JQL and use that filter in the "Workload Pie Chart" gadget in a dashboard. Then you have the option to select between "Time spent", "Original Estimate" or "Current Estimate".

In regards to reporting on sprints, I would say that the Agile Reports are still your best bet.

I hope it helps.

Best regards

Claus

 

Rashmi Ratnani
Contributor
June 3, 2024

Thanks for the reply @Claus Østergaard Pedersen

Then it's pretty much the same query that I posted above which I should try in the pie chart widget. Will give it a try. Thanks! :)

sprint report - community question.jpg

Rashmi Ratnani
Contributor
June 3, 2024

Hi again @Claus Østergaard Pedersen 

I am not sure if I missed anything.

I am unable to find the "estimate" fields in the statistic type dropdown.

Which fields should I be looking for? 

Thanks. 

Dashboard_sum of estimates.jpg

Claus Østergaard Pedersen
Contributor
June 3, 2024

Hi @Rashmi Ratnani 

From your screenshot I can see that you are working on Jira Data Center and that you are using the gadget called "Pie Chart" not "Workload Pie Chart".

Apparently, the "Workload Pie Chart" is no longer available in Jira Data Center: https://community.atlassian.com/t5/Jira-questions/Where-is-workload-pie-chart-report/qaq-p/1066469 

I thought you were using Jira Cloud, where the "Workload Pie Chart" is still available. 

So unfortunately you are not able to use the functionality described earlier.

Best regards

Claus

Rashmi Ratnani
Contributor
June 3, 2024

Oh! Too bad :( 

Thanks for your swift replies. 

/RR