I am creating a new KanBan Jira project from scratch and have created epics w/ tasks that have "Start" and "Due" dates. However when I view the "Roadmap" there is no visual "Gantt". The roadmap appears with the epic "rows" on the left, nothing appears on the right in the monthly columns? What do I have to do to get the Epics and Tasks to appear there?
Hello @brad_gerard
Welcome to the Atlassian community.
If you are accessing the Roadmap option from the navigation panel for the project/board then you are accessing the Basic Roadmaps functionality.
This document details how to schedule issues for a Kanban board for basic roadmaps:
Thank You @Trudy Claspill! This is exactly what I was looking for.
1) In Roadmap I went to top right "3 dots" > Configure Roadmap
2) Checked the "Child-level issue scheduling" which shows schedule lines as desired
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.