I conduct a sprint monthly and need to know the hours allocated to the sprint in terms of subtasks, but the hours should not accumulate with past sprints.
It may be the case that you have a board and you've set "Estimation method" to "Original tine estimate" or otherwise and then looking at a Sprint Report that shows in hours.
And then your question is about adding sub-tasks in to this report.
If you go to your sub-task, you'll likely see that the Issue itself does not have a Sprint field and is not directly added to a Sprint. This further discussed here:
Taking that discussion in to account, you may like to instead consider how you approach your usage of sub-tasks. If they are logging a material amount of hours, it may be a consideration to instead use a non-sub-task Issue Type such as Story instead for these tasks.
Ryan, I will read the forums and try to apply the methods you mentioned, thank you very much!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.