Hey dear Atlassian community,
one of my clients would like to remove the epics from the board but still wants to use the roadmap.
So far I always did that with the epic panel, but this time the client does not use the backlog.
Is there another way to remove the epics?
I cannot use the epic panel nor change the filter.. it's a dead end for me so far.
Greetings
Niklas
Is this for a company-managed or team-managed project?
And, if they are:
Are they are using a different workflow for epics? If so you could have a board column mapping which does not include the status values for epics.
Kind regards,
Bill
Hi @Bill Sheboy ,
it's a company-managed project and that was what I thought.
They are using the standard workflow.
Thanks for the verification, I will show them their options.
Greetings
Niklas