I add few basic tasks in big picture program. there is neither sub JIRA tickets nor dependency, hence 'status' column always shows 0% done. I'm wondering if there is a way for me to mark a basic task to be completed?
Thanks,
Cassie
Hi @Cassie Sheng ,
at the moment it's not possible to change a Basic Task status or progress in Big Picture.
However, they've shared in their roadmap that they plan to improve Basic Tasks features : they will add statuses, so you will then be able to show when a Basic Task is In Progress / Completed.
Let me know if this helps,
--Alexis
Dear Alexis,
Thanks for your prompt answer, it's useful, at least I know it's time to try other approach now.
B.R.
Cassie
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.