My question is for JIRA software NOT in cloud. (--> Its in the environment of my customer.)
Following situation:
I link issues with "is blocked by".
Example: Issue A is blocked by Issue B.
My assumption was the linking has an effect on workflow like:
Issue A is blocked by Issue B, that means I cannot move Issue A to "Done" before Issue B is resolved (because A is blocked by B).
So I thought it is similar to must have criteria, e.g. check off the acceptance criteria before moving it to "Done".
But so far the linking has no effect on workflow or rather what issue can be moved (or not) to "Done".
I have to add that this situation occurs in the JIRA environment at the customer, where I am a JIRA project admin, but no JIRA admin overall for workflows etc.
Is it a missing setting, where I would have to connect the links with status of workflow?
Or is it not possible in general?
In documentation I find information about linking issues, but not the consequence of that.
Best regards,
Georg
Hi @Georg Mayer - Unfortunately this is not possible natively, but you would be able to achieve this with a marketplace app like scriptrunner.
Hello @Mark Segall , thank you for your answer.
I was hoping for more functionality, but OK, good to know.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.