How can I set the team capacity number of hours and holidays in a sprint?

Susneha Patil August 18, 2018

How can I set the team capacity number of hours and holidays in a sprint?

2 answers

1 accepted

1 vote
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 18, 2018

Hello,

You would need a plugin for it. For example, Portfolio:

https://www.atlassian.com/software/jira/portfolio

karim.belhadj
Contributor
February 11, 2020

Hello @Alexey Matveev 

Could you please tell how can i see the team capacity in jira ? witch report using when we are in the sprint planing event , i would like to see the capacity of the team in live to stop pulling user story if we are getting the full capacity of the team !!

 

Regards

Karim

1 vote
Susneha Patil October 29, 2019

Hello Alexey,

Thank you for the answer. I figure, Portfolio add on should sever the capacity.

For holidays in a sprint though, it's available in 'Configure Board' page under Working Days section.

 