I can setup dependency on the EPICS and show them on the standard Roadmap. However, I am struggling to setup dependency on the issues and show them on the Roadmap.
I would like to leverage the standard roadmap to be a Gnatt chart like reporting tools to highlight dependency on different task or issue and highlighted them when task/issue delay and blocking other tasks.
Thank you.
Hi @da
You can link two epics together using Blocks issue link type. and it will show up on the roadmap but as you probably guessed it already the standard roadmap is a bit limited and won't let you plan at the story/task level. You would need Advanced Roadmaps for that or other roadmapping apps.
I hope it helps.
Ravi
Thanks Ravi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Ravi Sagar _Sparxsys_
I've created a Plan with the Epics in my project and dependencies to epics to other project are shown as a symbol (see picture). But how can I make the epics from other projects visible in the plan?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.