[Caveat: I'm new to Portfolio for Jira, and just trying it out.]
After creating a plan in Portfolio for Jira, and populating it with a few Projects, I excluded some issues (Epics, in this case) from the plan, and committed the changes.
How do I add one of the excluded issues back to the plan?
Hi @AdminTeam EMC,
You go to the configuration of your plan (the 3 dots next to your Plan's name) and under Source Data / issue sources click the Edit Sources button.
This will take you through the same wizard you used initially to build your plan. In the last step of the wizard, you will see an overview of the issues that will be imported. Right there you can find your excluded Epics and check the box for them to be imported again.
Thank you!
(That was totally not obvious, but it works perfectly.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This does'nt work for me : I've exclude stories from my plan and I can't have them back in my Plan.
Do you have any solution (except deleting my plan and restart from scratch) ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.