Hi all,
My team is using Jira to track capacity. We track capacity in % of time spent on a task on a weekly basis, not in hours spent (e.g., this week I spent 20h creating Jira tickets so I put in 50% in custom label on my ticket called "Creating Jira tickets")
My question is - can I create a chart to visualize how much effort (%) is each team member spending per week on their different tasks? How would I go about doing this?
Alternatively, if you have any better ideas on how to track percentage of time and visualize it, please let me know.
Jira is confusing
Thx and cheers
Irena
Let us first talk about storing this information in Jira.
Use Original Estimate field which is a system field.
Storing percentage in a custom field is a not really manageable solution in long run.
I hope it helps.
Ravi
Thank you, Ravi, for your answer.
The thing is - we don't use estimates nor hours to log our work.
Is there a way to visualise data put in other fields? not the system fields?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Using a percentage here makes it impossible to report. You need to be measuring progress / work in consistent numbers that mean the same thing. (50% of my week's work is not going to be 50% of your week's work).
Once you've moved to a proper estimate and/or work-log, (hours, days, story points, etc), you'll be able to use the built-in reports to do some of the basics, or look to the apps Ravi mentions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Wait, just to confirm - there is no way to visualize data from custom fields without additional apps, with the tools that Jira offers by default?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ah no, I see there are some charts and exports. Ok. Thanks all, I'll dig deeper!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes, there are some.
When you are looking through them, do not neglect the ones that talk about "sprints" (if you have Jira software). A sprint can use any (absolute) number as an estimate, so you might find there are reports or gadgets that can be pointed at your number field and give you some more options.
There are also a few that run off the estimate and/or work-log, but you would have to move to using the time-tracking fields to use them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
She says 20h = 50%. Hence, the problem for reporting is not percentage (units) as you are able to transforma percent into hours and vice-versa. As well you can transform hours into seconds or working days.
Jira is very very flexible and they are not using the standard way, but this dos not mean they cannot track capacity in that way.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is that true for every possible user? In real life, it's not.
%'s are not suitable for tracking, only numbers that represent a value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Units are totally irrelevant.
Jira stores worklogs in seconds internally, so you need some transformation to convert those records into the target unit for reporting,: hours for instance.
And percents can also be transformed to any other units.
Many organizations use custom fileds to track effort in alternative units, like costs in one or more currencies (USD, EUR, GBP, etc). An that is real World and it works. An international company might want to store costs along with the user's country currency symbol (10.000 $, 10.000 €, 10.000 £, etc). They are strings and not number. Many CEO and directors track work by money not hours, which is better suited for lower level managers,.like project or team managers. Tracking work in time units is better for planning. Tracking work in currency units is better for budgets. And even you can use arbitrary units like Story Ponits in Agile to track Sprints progress.
So units are irrelevant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That's what I said earlier.
Percentages are not a unit though, they are a ratio, and you can't usefully use them for reporting anything other than that ratio.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Well, Pablo is right - we measure effort in % because each work week consists of 40 hours (if someone works more than that, then they are over-worked).
True for all possible users.
The report doesn't have to have % in it, but I want to indicate that 100 is the top border, and everything above 100 (%) means the person can't get any more tasks - to put it simply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No, percentages are a ratio, not a unit. They are not suitable for tracking work (but they can be very useful as a report)
But you are using them as a unit, and if you want to call your units a percentage, that's up to you. But you are going to run into a case where they're not going to work as percentages at some point. Are you sure everyone will always have a 40 hour week? Never a part-timer or contractor?
You should obviously be putting the numbers into a numeric field, then you can use some of the reports to get a display of how much each person has, and more if you look at the apps Ravi mentioned (of course, there are a load more reports if you treat your numbers as something like story points, or you log work in days/hours)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.