How can you fix Control Chart report where shows variables instead of Day, Weeks, Hours etc?

Ian Johnsen May 8, 2019

The control chart seems to be displaying some sort of variable/constant placeholder, rather than the words for the times `days` `weeks` `hours`

 

Screen Shot 2019-04-22 at 11.19.35 AM (2).png

1 answer

1 vote
Bhushan Nagaraj
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 8, 2019

@Ian Johnsen , is this on Cloud or Server/Data Center? I would suggest raising a support request at support.atlassian.com for this one.

Ian Johnsen May 9, 2019

@Bhushan Nagaraj - Ahhh sorry forgot to mention. We are in Jira Server. I will raise a ticket with support.atlassian.

 