Dear @Joyce Costa,
to be honest, with one half sentence and two small parts of a screen shot we cannot help you. Can you describe your problem more precisely?
Thanks
Thomas
Sir @Thomas Deiler,
I want to know how to extract data (report) from activities that are stopped. In Jira you have an option in the workflow as a paused task. Each time I click on the interrupted option the system shows no interaction and has no traceability reg- ister for this action.
I also want to know how to generate report on the rotation of actions to reject the test of development (-1) minus one. This step is within the workflow of QA, Beta, Ready for Prod.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Joyce Costa,
ok, just to be sure, I understood you right. You have a custom made workflow (not standard from Atlassian) that has a transition "Interrupt" that will set the issue to status "Paused". When you press this button, nothing happens, right?
I guess, that this transition is instant, means no Screen is displayed, where you could add data.
So if I understood you correctly, you want do know more of those "Paused" isuses. Best you create filter, that returns only issues in status "Paused" of your project:
project = your_project AND status = "Paused"
For the second problem you described, can you please attach a screen shot of this workflow containing the -1 and +1 transitions.
So long
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Nop.
But do you have a team mate next to you, that can translate in English?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear @Joyce Costa,
as I said, save a filter with the upper JQL (search issue -> advanced, then copy/paste). Then add for example the show filter results gadget to the dashboard and select your saved filter. Now you will see all paused issues within one view.
The 2nd question:
The -1 is leading back to the same status - this is not at all wrong. But I guess there is a post function implemented in the workflow, that will decrease something. Can you click in detailed view of the workflow on the transition #121 and post a screenshot?
so long
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ok, thanks - doesn't look like there is an additional post function - there are 5 and that's the default value (normally).
I also want to know how to generate report on the rotation of actions to reject the test of development (-1) minus one. This step is within the workflow of QA, Beta, Ready for Prod.
So I don't get the very details of this quoted text - sounds like some google translate result. Can you please explain in other words what you would like to do?
so long
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
First problem - It's correct, when pressed the "paused" button nothing happens! Yes! I want to know how I can extract report of problems in the "paused" status in my project
Second problem follows screen capture of workflow