I have noticed that the time stamp within an issue when is moved to done does not match the time stamp within the burndown chart. Is there a separate time configuration for reporting? The issue done time stamp does match the Jira server time, yet the Burndown chart time stamp is 6 hours off.
Example:
Moved Task to done at 7:11 PM
Burndown Chart displays it was done at 1:11 PM
Hi @Keith Schug
It's possible that you are not setting the resolution field. Moving a ticket to done and setting a resolution are different concepts in jira workflows. To ensure that they are the same you have to ensure that the resolution is set via a transition screen or a postfuction that sets the resolution.l ti some value.
Go to the history and check when the resolution field was set vs when the ticket was moved to done.
I hope this helps.
I have my Jira instance setup to have a post function when an issue is moved to Done it has a Resolution of Done as well. Another thing is that all the times are exactly 6 hours different for every issue type.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.