How do I get Completed vs Committed tasks for previous sprints in Jira Cloud

Omar.Samad November 17, 2021

I need to get number of Issues Committed / number of Issues Completed

Also need to know Story points ratio. Is there any filter or query for that?

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Champion
November 17, 2021

That information for story points committed and completed is available in the Velocity Report under the Reports section of the Scrum boards.

I'm not currently aware of a way to get that information for issue counts.

Omar.Samad November 17, 2021

thank you Trudy for the answer.

I was looking at adding a gadget to the dashboard showing the % of items completed / committed.

Trudy Claspill
Community Champion
November 17, 2021

Natively Jira doesn't support a query that will get you the information. You will need to look at apps that extend the JQL capabilities, or look at apps that add more sprint-related gadgets for the dashboard.

Like Omar.Samad likes this
Leesa Haslam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 11, 2022

The Insights for the Active Sprints show this information. 

I do not know (but would like to learn), if this information persists once the Sprint is completed. 

Like Trudy Claspill likes this
Pablo C. Garcia August 30, 2022

 

I´m being unable to see the Velocity Report under the board. Is there something I´m missing?

Untitled.jpg

Trudy Claspill
Community Champion
August 30, 2022

@Pablo C. Garcia 

Welcome to the community.

Are you using Jira Cloud or Jira Server/Data Center?

Are you working with a Team Managed project or a Company Managed project? It will say at the bottom of the navigation pane on the left.

Please confirm you are working with a Software project. That will show at the top of the navigation pane below the project name

Pablo C. Garcia August 30, 2022

It´s Cloud based; Company Managed; Software project. 

Trudy Claspill
Community Champion
August 30, 2022

Your screen looks different than what I see in Jira Cloud when viewing a Scrum board for a Company Managed Software project and selecting the Reports option.

Can you provide a full screen image? Black out anything that is confidential.

What is the filter on which the board is based?