Software Boards (Scrum and Kanban) are configurable and you can add columns under "board configuration -> columns".
Core boards follow your workflow - add a status to the workflow, and it will appear as a column.
Hi,
Thanks for the reply. I have added a status to my workflow called 'In Test' and assigned open to it. How do you change the order of the status's? I want my 'In Test' to be before 'Done'.
Roger
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Status don't really have an order in a workflow, the paths between them define what order you can move through them in (or back, or around).
On the boards, you would add a column for "in test", map the status into it and then move it by dragging the column tops around in the board configuration
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.