How to add more report in JIRA Next Gen

Binsar Tambunan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 10, 2019

Hi Guys,

 

I a new person who uses JIRA Next Gen. I see so many different features between Classic and NextGen. Especially in the report feature.

Could you please guide me how to add more report feature such as  : 

  • Sprint Report
  • Control chart
  • Version report

 

Thank you,

 

2 answers

2 accepted

0 votes
Answer accepted
Ivan Teong
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
December 11, 2019

Hi @Deepanshu Natani and @Binsar Tambunan

 

We just released the Sprint Burndown for next-gen that took the best elements of Classic's Sprint report and Burndown chart, while introducing new functionality: https://community.atlassian.com/t5/Next-gen-articles/We-are-reinventing-the-Sprint-burndown-for-next-gen-projects/ba-p/1192403

Let me know if that works.

 

Regards,

Ivan

Product Manager, Jira Software Cloud

jpbruno
Contributor
June 4, 2020

I want to enable the sprint burndown chart that shows me the time remaining. Considering that we split user stories into tasks, I don't see an option to keep doing that...  Could you please help?

Like Nikhil Nair likes this
0 votes
Answer accepted
Deepanshu Natani
Community Champion
December 10, 2019

Hi @Binsar Tambunan 

At present, these reports are not available for next-gen projects.