I need to list down Epics, Stories, Tasks & Sub-Tasks under a particular Portfolio Epic in Backlog.
Tries to below JQL query:
(project = <projectkey> AND "Parent Portfolio Epic" = <key>) AND (issuetype = Story OR issuetype = Sub-Task OR issuetype = Epic)
It just returns the stories. Is there a way to do it?
Hello @Rakshatha Shetty
You can use the following query to list all the child issues of an portfolio type.
issuekey in childIssuesOf("ABC-248")
here ABC-248 is the key of the issue which is present in portfolio and will display all it's children
Hi @Tarun Sapra ,
Thanks for your response!
The query is reverting the Stories & Epics present under the particular Portfolio Epic. Stories have few sub-tasks associated with it. Is it possible to list down sub-tasks as well?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Rakshatha Shetty
Which version of JIra and portfolio do you have, as using the above query I am getting the sub-tasks of the stories as well.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Tarun Sapra ,
I'm using JIRA 8.2.1 & Portfolio 3.3.1.
I have created a quick filter for the board using the query & trying to access it in the backlog section. I hope I've done it right.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Rakshatha Shetty
In the backlog section you don't see sub-tasks, this is a Jira feature which is why you are not able to see the sub-tasks in backlog.
This has been discussed many times on the community.
If you feel my answer helped you, please accept/upvote . thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Tarun Sapra
That makes sense. As per my understanding the query should display the sub-tasks on the sprint board. I guess it is working that way for you. But the query isn't returning the sub-tasks on the sprint board as well for me. Any idea on what could be wrong?
Thanks,
Rakshatha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Rakshatha Shetty
Can you check if the query is returning sub-tasks in the issue navigator view? and please share screenshot of the board configuration and column configuration. It should ideally display sub-tasks on the active sprint view and not the backlog view of the board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.