How to get sum of story points for particular sprint

Ramesh Krishnan
Contributor
February 27, 2025

I would like to see total or sum of story points for given or particular sprint. Where to see this value.

2 answers

2 accepted

4 votes
Answer accepted
Nikola Perisic
Community Champion
February 27, 2025

Hello @Ramesh Krishnan 

For the upcoming sprints, the sum can be shown on the top right corner of the backlog

Screenshot 2025-02-27 at 10.59.43.png

Stephen_Lugton
Community Champion
February 27, 2025

@Ramesh Krishnan this includes the current sprint as well as upcoming sprints

 

Like Ramesh Krishnan likes this
Ramesh Krishnan
Contributor
February 27, 2025

is there way to see the sum for past sprint or completed sprint?

Nikola Perisic
Community Champion
February 27, 2025

@Ramesh Krishnan 

For past sprints, you cannot see the sum with the native Jira feature. You can check this article:https://community.eazybi.com/t/how-do-i-sum-the-story-points-of-the-last-3-sprints/10063

1 vote
Answer accepted
Stephen_Lugton
Community Champion
February 27, 2025

@Ramesh Krishnan for completed sprints you can look in the reports section from the left sidebar and choose either velocity or sprint reports