How to lock "time remaining" field in Time tracking.

Dmitri Stryuk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 4, 2021

Hello.

 

Please advise how can I lock the "time remaining" field in Time tracking!!!

Usually, when you add hours to the "time spent"  the "time remaining" calculates automatically (Original estimate-Time spent=Time remaining)

Jira 1.png

This works fine unless somebody cleans or manually corrects the field "Time remaining" when tracking time spent... When this happens appears a yellow strip and starting mess, especially with a big amount of time.

To avoid this issue and not to investigate who did this on the project, I'd like just to lock the field "Time remaining".

 

Please help

Thank you.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 4, 2021

This can't be done.  Time remaining is not really a field in its own right, it is part of the time-tracking field.  You can't stop people changing it without stopping people changing the other fields that are part of the time tracking as well.

Dmitri Stryuk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 5, 2021

Thank you for the answer, @Nic Brough -Adaptavist- 
I have another related question about the Tracking time topic. 

When we change "Original estimate" (and we have some already logged time), "Time remaining" doesn't calculate automatically (considering the new "Original estimation" number). So I have to calculate manually the "time Remaining" is it correct behavior, or it's a bug?

Thank you @

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 5, 2021

That's right - the original estimate is supposed to remain the original, and time remaining is supposed to be measured against the original estimate.