How to maintain a child-parent relationship between a Story and Task like we have bwn task & subtask

Vivek Garg
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 2, 2022

I wanted to establish a child-parent relationship between task and story as we can maintain in subtask and task.

1 answer

1 accepted

2 votes
Answer accepted
Mohamed Adel
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 2, 2022

Hi @Vivek Garg  Welcome to the community 

no extra effort required as long as you can add subTask under story then it is automatically added with Parent/Child relation linkType. similar what you are doing with Task

Thanks 

Mohamed Adel 

Vivek Garg
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 2, 2022

Thanks @Mohamed Adel ... That is what my understanding as well but when i am creating the plan and in hierarchy selecting Feature to the subtask, it is not showing the task under the story otherwise everything else (Story under Feature, Subtask under Task) is showing correct mapping. Ex- IMG_8096.jpg

Mohamed Adel
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 2, 2022

Hi @Vivek Garg 

I'm sorry I read the question wrongly , Task & Story are in the same level and you can not add one of them under the other one. 

Thanks 

Mohamed Adel 

Suggest an answer