I am using Jira as non-admin user,
I update a task from TO DO to IN PROGRESS. But this task is not showing in current sprint 0 (ACTIVE SPRINT) but I can search and see it available in the project board and It is included in Sprint as well.
I dont know what exactly happened. But I guess it is due to change of, the workflow of in the middle of sprint.
Do you have idea on what is the cause. of above issue and how to make the task visible in the ACTIVE SPRINT again?
Thanks
If you change the workflow you have to make sure that any new status is also mapped to the board columns. If you have board admin access, go to Board settings > Columns and make sure all statuses are mapped.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Nham Thanh Tung,
If you mention a workflow change, it does happen that a new status is not mapped to a column on the board.
A board administrator can verify and fix this by navigating to the board settings. On the columns tab, unmapped statuses can be dragged to a column on the board to make them appear on the board (again).
Hope this helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.