Hello team,
We have started working on release from last month and we have completed three sprints and 4th sprint is started under this release in project A.
Now we got information from project manager that all these sprints and efforts has to be added in new project B.
Do we have any way to migrate all these completed sprints, ongoing sprint, version and efforts logged to B project?
Thanks!
I just did it following the below steps:
1. Put all items you need to transfer to a new project in a separate sprint,
2. Select all tasks
3. Right click on any task and select Bulk Change
4. Follow the steps, you should have the sprint in the new project (if there are any tasks which couldn't be transferred, you will have the same sprint in the old project as well. Relationships between the tasks will be lost.
Hi @Dnyaneshwar Ramesh Borase,
As far as I know, Sprint is not strongly associated with Project. The information displayed in Scrum Board depends on the configuration of the Board filter. You can try the following two ways to handle this case.
1. Modify Project A's Board filter to include all Issues of Project A and Project B.
2. Move Issue from Project A to Project B and create Project B's exclusive Scrum Board.
Hope this help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank for the reply.
Can we migrate all version and efforts logged from project A to B project?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Dnyaneshwar Ramesh Borase,
The effort information is stored in the Issue and can be moved to Project B synchronously.
However, the version cannot be moved directly to the new project. It is recommended that you manually generate the version in Project B. When you move the Issue, the system will prompt you to select the version that matches the project B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI, I've a similar problem, the issue is that when I moved the issue from project A to project B I loose the connection with the original sprint.
Why is this happening?
I can't reassign the issue to the closed sprint
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.