Is there any way each task associated to an Epic shows its time bar on the Roadmap section?
Currently only appears the timebar for the Epic card itself but not for the Tasks inside that epic:
This is the limitation of the basic project specific roadmap. You would need to either use Advanced Roadmap (Jira Premium plan) or use an app like BigPicture.
I hope it helps.
Ravi
Or, like Structure.Gantt :)
You can use this link (or create your own) @Nacho García-Robledo to check out more options:
https://marketplace.atlassian.com/addons/app/jira/cloud-fortified?hosting=cloud&moreFilters=vendorSupported&query=gantt
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks @Ravi Sagar _Sparxsys_ & @Dave Rosenlund _Trundl_ !
Unfortunately both options require further investment so for the moment I think there is no free option to cover this demand.
Nevertheless, I appreciate your answers!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.