Does anyone know how to use the formula in Structure to calculate the sum of "original estimates" of any incomplete tasks? For example, If an epic has 2 tasks, and each task takes 1 day, then the total original estimate for the epic is 2. But if 1 task is done already, the remaining estimate for the epic should be 1. Anyone knows how to do this?
Hello @Jessica Wang
I'll repeat the answer that I posted to you in another post, just in case anyone else finds it here. You can do it with a formula like this:
sum{originalestimate} - sum{if status = "done": originalestimate}
Please reach out to us directly at our support portal if you need our help with anything.
Best regards,
Stepan
Tempo (the Structure app vendor)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.