If I want explain it with an example , I can say , Is it possible to wait starting subtask B when Subtask A has Done Status,
Hi @soheila sarabandi ,
Your requirements are not described very clearly, but I feel that Jira automation should be able to cover your needs.
https://support.atlassian.com/cloud-automation/docs/jira-cloud-automation/
Hi @Ollie Guan
thank you
I meant for example I have 3 subtasks (Subtask A,SubtaskB,SubtaskC) related to a story, and I want to know How I can create a Finish to start relation between Subtasks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
#1: Am I understanding correctly that you are trying to prevent a status change to "In Progress" for SubtaskB if the status on SubtaskA is not set to "Done"?
#2: Or are you trying to automatically set SubtaskB to "In Progress" when SubtaskA is set to "Done"?
Jira does not have a built in feature for either of these. #2 could be accomplished with the Jira Automation feature, possibly. #1 might be able to be accomplished through customizations of the workflow that applies to Sub-Tasks, if you are using a Company Managed project. Customization of workflows for Team Managed projects do not yet support having different workflows for different types of issues.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.