In Backlog, show "Status" on right, not under the key/summary on the left.

Maryellen Russo
Contributor
October 13, 2022

In an old team managed project, in the Backlog view, I could get the Status to appear on the right, along with Priority and Assignee.  

old.png

New project that is company managed, in the Backlog view, the Status appears on the left, under the key and Summary/Title. 

new.png

Is there any way to get the Status to appear on the right, like in the old team managed project?

Thanks for your insight!

1 answer

0 votes
Mikael Sandberg
Community Champion
October 13, 2022

The short answer is no, you cannot control where the status is displayed on the board.

Maryellen Russo
Contributor
October 14, 2022

Thank you.

Like Mikael Sandberg likes this
Maryellen Russo
Contributor
October 14, 2022

One follow up question Mikael.  Is there a way to easily change the board to be a board where we can see that status on the right?  Whether that means changing it to a team managed board or whatever. 

Thanks again for your insight. 

Mikael Sandberg
Community Champion
October 14, 2022

Yes, if you go to board settings you can change the card layout. You can add up to three fields that you want to see on the board.

Screen Shot 2022-10-14 at 11.05.33 AM.png

Maryellen Russo
Contributor
October 14, 2022

Great. I did that. But they show up on the left and not the right. Any suggestions to maybe change the type of board/project it is? 

Mikael Sandberg
Community Champion
October 14, 2022

Unfortunately there is no option to control where those fields are showing up...