If i make the ticket to on Hold, still the ticket is calculating the date and it is moving over due. How to manage this on JIRA?
I am sorry, the question is not clear.
The due-date on an issue does not change unless a user edits it. If your due-date is changing, then you must have installed something that changes it on transition.
Or, you are not looking at the due date, it's something else?
Sorry for Not Being Clear.
While creating a issue, user can set the due date.
And I have made the DUE DATE non-editable after creating a issue.
So When a user put the issue on Hold due to some reason. And when they start to work again, it is not possible for him to change the due date.
Is there any feature in jira to increase the due date by 1 day when the issue is on hold status.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Ah, I see, it's not changing at all, but you need it to.
There's no way to do this with plain JIRA, but there are a number of add-ons that provide a post-function that can update the due-date when used.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.