I currently have in my schema estimation in user points
Is it possible to modify it to estimation in days?
Hello,
You should add the timetracking field to the screens, which are linked to the issues, where you want to track estimation in days.
Hi,
Time tracking is about logging time, while I'm looking for estimation phase, so it can be further used for the sprint planning etc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Open the board, which you use, go to the Board Settings -> Estimation and choose Original Time Estimate.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
is this available also in kanban board? can't find it there
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is not available for the Kanban board. I would add the timetracking field to the screens and use this field
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
ok, tnx
i created a new sprint project and configured per your suggestions above. working as expected
many thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.