We want to know if it is possible to only display 'time tracking' as hours, not to set as days and week as we juste want to see hours. Thank you for your help ! 

1 answer

1 accepted

1 vote
Answer accepted
Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 3, 2022

@Amelie Allain Yes, this is configurable.

 

Go to

settings -> issues -> Time Tracking

and modify the

Time display format
By default it is "Pretty (e.g. 4 days, 4 hours, 30 minutes)", but you can change it to "Hours" for example.
Amelie Allain
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 6, 2022

Yes, it worked. Thank you for your help Jakub !  Much appreciated 

Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 6, 2022

It is great that it worked.

 

Please accept the answer to help others with similar questions.

Henry Cheung
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 29, 2023

In project settings, I cannot locate the "issues" and "time tracking"

Could you please specify where they are? Thanks.

Courtnie Ridgway
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 8, 2023

I have issues, but not time tracking. I am assuming that that is not a project setting but an admin one. Is that correct, @Jakub Sławiński ?

Jakub Sławiński
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 10, 2023

Yes, these are an admin settings:

Screenshot from 2023-09-11 08-43-55.png

 

You will see the time tracking when you click them:

 

Screenshot from 2023-09-11 08-44-21.png

 

 

Please let me know if you need any more explanation.