Is it possible to see a total count of all the estimated time when creating a sprint?

Arnoud Aarnoudse May 9, 2018

When we are planning a sprint we would like to make sure that the SUM of all the estimated times from all the issues is not too high, how could we easily see this when creating a sprint? We would like to see this on the board itself, kinda like Trello has the addon to show the points on top of a list.

1 answer

1 accepted

0 votes
Answer accepted
Fazila Ashraf
Community Champion
May 9, 2018

Hi @Arnoud Aarnoudse

Yes, you can.. Click on the ... and you get the 'workload by assignee' and that has the total story points also.

 

tot_sp.PNG

Arnoud Aarnoudse May 9, 2018

Thanks! This will be good to know for later, but I failed to explain myself properly, sorry.

What I meant is, can I get this kind of overview BEFORE we have to start the sprint?Untitled.png

Fazila Ashraf
Community Champion
May 9, 2018

@Arnoud Aarnoudse , yes you can.. You have that right in the screen you pasted..

You see 'Estimate' as 0 at the bottom of your screenprint? That gives you exactly that.

Arnoud Aarnoudse May 9, 2018

Thank you so much! It was on 0 because I still had it set on Story Points instead of time estimate, I changed it by going to the board configuration.

You have been a great help!!

Fazila Ashraf
Community Champion
May 9, 2018

Glad to be of help! 

Could you also accept the answer (tick mark before the answer) ?

Arnoud Aarnoudse May 10, 2018

Ah I was looking for that but couldn't find it, that was subtle. Thanks again! :)