Is that possible to create two parallel SPRINT to occur at the same time in the same project?

Jay May 14, 2018

We have a big team where people work in separate tecnologies. Thus the necessity to share the team below the same JIRA project but let them (the sub-teams) to prepare their sprint separately but start all three sprints at the same day. 

2 answers

0 votes
Walter Buggenhout
Community Champion
May 14, 2018

Have a look at the parallel sprints feature for this.

Jay May 15, 2018

Hello Walter,

Thank you very much!

0 votes
Deleted user May 14, 2018

Hi @Jay,

It is possible if you enable Parallel Sprints

https://confluence.atlassian.com/jirasoftwareserver/using-parallel-sprints-938845513.html

You will be able to set and start multiple sprints in the same project.

Hope this helps

Jay May 15, 2018

Thank you Danny! I will request the JIRA admin to find this topic there and make it available to the project of my team. 