I'm using the project timeline in a Kanban board within a project (not in Advanced Roadmaps.)
My hierarchy is Theme < Initiative < Epic < Story < Subtask. Themes exist in a separate overarching project to track cross project dependencies at the Initiative layer and below, Initiatives are tracked in the product team projects.
All the issues, including Initiatives are showing on the Kanban board and the Epics are correctly linked as "children" of the Initiative using the Parent Issue field. However, only Epic and below are showing in the timeline view.
The documentation in the section What does the project timeline show? indicates that hierarchies above Epic are possible.
The default parent issue type in Jira Software is Epic, which is what we use in this documentation. However, this is a dynamic value based on how your administrator configures the parent issue type. For example, if your project uses feature as the parent issue type, you’ll see Create Feature.
Is there something I am missing in my setup?
Hello @Scott Theus
The Timeline feature is not capable of showing the levels above the Epic issue.
What you are quoting is a reference to another feature that allows changing the name of the Epic issue type from "Epic" to "Feature". The Timeline still can only show up to the level where the original Epic issue type resides, and nothing above that.
Thanks @Trudy Claspill I suspected as much, but thanks for confirming.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.