Issue with "TO DO" Status is displayed in "In Progress" column of projects Kanban Board

Manisha Pardeshi October 12, 2022

I created a jira issue for a project. The issue status is "TO DO" by default.

When i view the Kanban board, this issue is displayed in the "In Progress" column.

Why is this happening?

How can I see all the issues with "TO DO" status in "TO DO" column of my Kanban Board?

1 answer

1 accepted

0 votes
Answer accepted
Mark Segall
Community Champion
October 12, 2022

Hi @Manisha Pardeshi - In your board settings, it's likely that the To Do status is inadvertently mapped to the In Progress column

Manisha Pardeshi October 12, 2022

Hi Mark, how do i check this mapping?

Mark Segall
Community Champion
October 12, 2022

Inside your project board view, select the ... option at the top right.  Depending upon whether your project is configured as Team-Managed or Company-Managed, you'll see one of the following options:

Team Managed

2022-10-12_13-21-38.jpg

Make sure Columns and Statuses is selected from the left navigation

 

Company Managed

2022-10-12_13-22-25.jpg

Make sure Columns is selected from the left navigation

Like Manisha Pardeshi likes this
Trudy Claspill
Community Champion
October 12, 2022

Click on the ... button in the upper right corner of the board.

Select Board Settings (if Company Managed project) or Configure Board (if Team Managed project).

If it is a Team Managed project, the Columns with their mapped statuses will display. If it is a Company Managed project you will need to select the "Columns" options to show the information.