Hi all,
Is there any way to get Portfolioplan to update progress-bar related to issues status.
I whould like to see Epic status 50% if 5 out of 10 "child issues-story-task" is set to done-status.
Below from documentation...but for me it will not happen ?
The plan is built by JQL filter if thats any help...
Thanks in advance!
//PEG
Calculating Progress for Issues without estimates
If the issue does not have estimates:
If the issue is resolved (Resolution field is not empty), the progress is 100%.
Otherwise, the progress is 0%.
Hi Per,
Which version of Jira portfolio do you use?
Ok, could you show wich JQL filter is used for the issues in your plan?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think I first need to understand if "my" logic could be supported in any way ?
5 out of 10 issues-storys in Epic set to status DONE = 50% progress on Epic...regardless of any estimate or no estimates
IF thats possible then I need to find correct JQL/Filter for my purpose.
I understand that progress calculation in portfolio counts in a different way...out of the box
//Per
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, yes it can support that logic. You found the correct documentation. If you don't see the progress correctly it may be because some issue types are not considered in the JQL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.