Hi all,
Hi @Pooja
Guess the date format in the jira import is dd/mmm/yy h:mm.Try changing the format to dd/mm/yy and import it should import your csv file.
or import the value as dd/mmm/yy h:mm (eg: 15/jan/18 01:22 )
Cheers,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Your date should look like this:
22/Oct/18