Hi,

 

Our Reporting for the sprint is showing a card AE-1090 as Incomplete, even though it was not committed to the sprint. Its history shows it was in the sprint a couple of months ago, but not when the sprint started.

Reporting an inaccurate 8 points uncompleted is significant.

This must be a bug, but would like to resolve for end of quarter reporting. 

Any help would be appreciated.

 

Thanks

Narelle

 

Screenshot 2022-12-06 at 1.57.09 pm.png

Screenshot 2022-12-06 at 1.39.55 pm.png

 

 

1 answer

1 accepted

0 votes
Answer accepted
Narelle Sartain December 5, 2022

I ended up re-opening the sprint, deleting the card, and closing the sprint again.

Piyush A (STR)
Community Champion
December 5, 2022

Did you cloned those tickets? Generally a cloned ticket can carry over the Sprint too