Link 2 scheduled issues from different projects with automation

Tal Stanek March 10, 2022

Hi there

 

I am trying to create 2 scheduled issues in 2 different projects and link between the 2.

All through automation.

 

The issues are created just fine, but the linkage is not happening.

I attached 2 screenshots.

 

Thanks!

Screen Shot 2022-03-10 at 14.16.59.pngScreen Shot 2022-03-10 at 14.17.27.png

1 answer

0 votes
Mark Segall
Community Champion
March 10, 2022

Hi @Tal Stanek - It looks like what you have would theoretically work. However, I'm wondering if a refetch is required to capture the "Most Recently Created Issue". can you try using the smart value {{createdIssue}} instead?

Tal Stanek March 13, 2022

Thanks

I'm not sure how to do that.

John Funk
Community Champion
May 15, 2022

Just add a new Action between the two create issue objects and choose Re-fetch issue data