Missing Story Points indicator on Scrum board

Aleksandra December 14, 2021

Hi, See the photo.
I cant get the 8 SP value in the place it should be (it is working correctly for the other team). 
The place with "-" has information "Unestimated" even when the actual SP is shown ("8"). How I should change the settings?

jira SP.PNG

1 answer

1 accepted

0 votes
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 14, 2021

Hi @Aleksandra 

This appears to be a board item for a company-managed project.  Is that what you are using?

And, which field are you entering your values in: Story Points or Story Point Estimate?  Story Points are used by company-managed projects, and Story Point Estimate is used by team-managed projects.

Kind regards,
Bill

Aleksandra December 15, 2021

Hi Bill,
I fixed it by ticking "None" in Settings -> Estimations.

Like Bill Sheboy likes this
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 15, 2021

@Aleksandra did you also remove the extra Story Point field from your card settings? 

Normally when the estimation statistic is "none" the story points display where you were seeing the hyphen.  Thus the extra field on the card would not be needed.

Aleksandra December 16, 2021

Yup, I removed the filed at the same beginning as this result I got was not the one I wanted to have.
Thanks!