Hi,
I want to move a task that has been nested under the wrong project/cost center to another project, together with the logged hours.
Can you please let me know if when I move (migrate) an issue i.e. a task to another project, will the logged hours from that task be deleted from the original project and transferred to the cost center of the new project?
Both projects would be company managed.
Thanks,
Ana
You can think of "Logged hours" as a property of each task (not project).
So if you move an issue from one project to another, logged hours follows it - the same as description, summary, assignee etc...
So if you are looking on a total number of logged hours on projects level, then the amount of logged time in source project will be reduced and the amount of hours in target project will be increased
Great, thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.